There are several steps to implementing your project; we have listed these below.
- Confirm funding, any conditions, claiming procedure and cashflow provision.
- Agree your consultant’s implementation stage scope of works, including:
- confirming all consents are in place, and all conditions discharged
- confirming grid connection dates and the payment schedule
- chairing regular meetings, including risk register and programme review.
- Instruct your installer to begin, evidencing insurances etc prior to the site start.
- Promptly attend to queries, variations, unforeseen challenges and changes.
- At the appropriate time (close to or at completion) you will need to:
- confirm insurance cover to operate from installation completion
- contract your operation and maintenance requirements.
- Secure payment for generation exported to the grid. You could consider:
- the Smart Export Guarantee (SEG), available to projects under 5MW
- a PPA with an energy supplier
- securing a Contract for Difference at auction.