Introduction

The communities of Knoydart, Muck, Eigg and Foula are not connected to the mainland electricity grid in Scotland. Instead, these communities own and operate their own energy generation, distribution and storage systems. This is achieved by using one or more of the following to generate their own electricity:

  • wind
  • solar
  • hydropower.

These communities have no direct road to the mainland, which means that access, travel and transport can be challenging. This can create difficulties in running and maintaining off-grid schemes, especially when trying to maintain a constant supply of electricity for these communities.

Knoydart, Muck, Eigg and Foula applied for funding from the Scottish Government’s Community and Renewable Energy Scheme (CARES) to help overcome these challenges. The total funding amount awarded from CARES was £2,448,463.25.

Houses in Muck by the water.

The aims and objectives of each community

The challenges of developing energy projects in remote places

What impacts have the projects had?

Eigg Electric Ltd, Foula Electricity Trust and Isle of Muck Power Ltd have reported that the resilience of their grid has been improved as a result of their projects and an increase in ability to both control and manage systems. A spokesperson from Isle of Muck Power Ltd stated that “The project on Muck has been a real leap forward for our power scheme in terms of both capacity and resilience”.

Eigg Electric Ltd’s new infrastructure will allow the installation of three new 100 kW wind turbines in the next phase of its decarbonisation journey.

For Foula Electricity Trust, the upgrading of the T6 transformer has also enabled the stable operation of communication infrastructure, improving community access to mobile and internet services. A newer generation of inverters allow Foula Electricity Trust to monitor and remotely access real time performance parameters of the network.

Foula Electricity Trust and Knoydart Renewables Ltd can now support future peak power requirements and – thanks to battery storage – can reduce the use of diesel-fuel-powered backups.

Knoydart Renewables Ltd’s new turbine runner has resulted in the peak power output of the scheme increasing from 320 kW to 400 kW, providing peak power headroom for the years to come.  The undergrounding of cables has improved the reliability of the system and will allow new connections to the grid. Knoydart Renewables Ltd’s project manager from Energy Mutual stated, “This project has reduced power outages to zero to date. While in the past, the overhead lines were regularly getting damaged by falling tree branches or geese flying into the lines.”  Smart meters will also allow Knoydart Renewables Ltd to accurately track energy demand and make more informed plans for future network and generation requirements.

The benefits of bringing in external support

How CARES supported projects beyond funding

Energy Mutual, which provided project management support for Knoydart Renewables Ltd, Muck Power Ltd, and Foula Electricity Trust, is part of the CARES support framework.

CARES supported each project during the funding stages, reviewing land titles, technical proposals and contracts to make sure all information was correct.

CARES funded the feasibility work undertaken by Eigg Electric Ltd, which informed the project’s work plan and provided general advisory support throughout the project.

CARES also helped Eigg Electric Ltd get a funded learning exchange through the Scottish Community Alliance by connecting Eigg Electric Ltd with someone who could support its application.

Lessons learnt

A key learning across all the projects was to avoid scheduling projects during autumn and winter, as the weather conditions in these seasons caused costly delays. The importance of project management was also a recurring theme.

A spokesperson from the Isle of Muck Power Ltd shared “The greatest challenge has undoubtedly been managing timelines. With the limited number of contractors capable of delivering this type of complex multi-disciplinary project, timelines have tended to stretch.”

Knoydart Renewables Ltd’s project manager from Energy Mutual stated, “I wish we had a clearer idea of lead times for transformers as they took longer than expected to manufacture and deliver to the site but in the end this aligned with the civil contractor’s cable laying timeline due to weather delays.”

Eigg Electric Ltd highlighted that relying on volunteer time also posed a challenge due to limited availability and several complex projects taking place at the same time. Eigg Electric Ltd also found that it benefited from having experienced contractors on board who were willing to operate at a reduced cost. However, as this work was being done at a lower rate, it was challenging to keep to funders’ timetables.

Other parties involved

Energy Mutual provided consistent single-point-of-contact project management support to Knoydart Renewables Ltd, Isle of Muck Power Ltd and Foula Electricity Trust.

Donfield Consulting set the design requirements for the technical scope for suppliers to tender against for the cabling contract for Knoydart Renewables Ltd.

Enerveo was the main contractor for Isle of Muck Power Ltd and  Foula Electricity Trust.

Foula Electricity Trust used Wind & Sun for its inverters and received additional funding from the Shetland Islands Council and Highlands & Islands Enterprise.

Eigg Electric Limited worked with trusted suppliers: Wind & Sun, Bowers Electricals Ltd, and Russet Engineering, as well as engaged with StorTera, who advised on, and supplied, a bespoke EV charging system.

Knoydart Renewables Ltd contracted Gilkes for the turbine runner installation and StorTera for storage batteries. Alongside Energy Mutual, it got support from the University of Strathclyde in 2022 for smart meter demand management trials.