Balmurrie Fell (Artfield Fell Extension)
Overview
Project details
Funds spent this period
£0Project address
Balmurrie Fell, Newton Stewart, Dunfries & Galloway. DG8Technology
Onshore WindCommunity benefits offered
YesCommunity shared ownership offered
NoProject owner
Project owner name
SSE RenewablesProject owner website
https://www.sserenewables.com
Contact email
colin.mcmillan@sse.com
Overview
Community benefits details
Community engagement
Project stage when community engagement on community benefits began
In constructionFunds this project contributes to
| Package name | Balmurrie Fell Community Fund |
| Fund website | https://www.sserenewables.com/communities/ |
| Planned start date | |
| Actual start date | 11/01/2012 |
| Planned end date | 10/01/2037 |
| Actual end date | |
| Memorandum of understanding date | 01/05/2013 |
| Date community benefit agreement completed | 01/05/2013 |
|
Link to community action plan (or similar)
|
https://www.newlucect.org/community-action-plan/ |
| Fund administrator | Developer |
| Fund administrator more details | |
| Community benefit package mechanisms | |
| Financial structure used to determine community benefits | Payment: per MW installed |
| Who makes decisions on what to fund? | Community Panel |
| Regular review of community benefits package | Yes – every 3-5 years |
| Local authorities | |
| Community councils | New Luce, Old Luce |
| Package name | Sustainable Development Fund Dumfries and Galloway |
| Fund website | https://www.sserenewables.com/communities/ |
| Planned start date | |
| Actual start date | 12/09/2013 |
| Planned end date | 10/09/2038 |
| Actual end date | |
| Memorandum of understanding date | 11/01/2021 |
| Date community benefit agreement completed | 11/01/2021 |
|
Link to community action plan (or similar)
|
|
| Fund administrator | Developer |
| Fund administrator more details | |
| Community benefit package mechanisms | |
| Financial structure used to determine community benefits | Payment: per MW installed |
| Who makes decisions on what to fund? | Stakeholder panel |
| Regular review of community benefits package | Yes – every 3-5 years |
| Local authorities | |
| Community councils | All community councils in Dumfries and Galloway |
| Package name | Balmurrie Fell Community Fund |
| Fund website | https://www.sserenewables.com/communities/ |
| Planned start date | |
| Actual start date | 11/01/2012 |
| Planned end date | 10/01/2037 |
| Actual end date | |
| Memorandum of understanding date | 01/05/2013 |
| Date community benefit agreement completed | 01/05/2013 |
|
Link to community action plan (or similar)
|
https://www.newlucect.org/community-action-plan/ |
| Fund administrator | Developer |
| Fund administrator more details | |
| Community benefit package mechanisms | |
| Financial structure used to determine community benefits | Payment: per MW installed |
| Who makes decisions on what to fund? | Community Panel |
| Regular review of community benefits package | Yes – every 3-5 years |
| Local authorities | |
| Community councils | New Luce, Old Luce |
| Package name | Sustainable Development Fund Dumfries and Galloway |
| Fund website | https://www.sserenewables.com/communities/ |
| Planned start date | |
| Actual start date | 12/09/2013 |
| Planned end date | 10/09/2038 |
| Actual end date | |
| Memorandum of understanding date | 11/01/2021 |
| Date community benefit agreement completed | 11/01/2021 |
|
Link to community action plan (or similar)
|
|
| Fund administrator | Developer |
| Fund administrator more details | |
| Community benefit package mechanisms | |
| Financial structure used to determine community benefits | Payment: per MW installed |
| Who makes decisions on what to fund? | Stakeholder panel |
| Regular review of community benefits package | Yes – every 3-5 years |
| Local authorities | |
| Community councils | All community councils in Dumfries and Galloway |
| Package name | Balmurrie Fell Community Fund |
| Fund website | https://www.sserenewables.com/communities/ |
| Planned start date | |
| Actual start date | 11/01/2012 |
| Planned end date | 10/01/2037 |
| Actual end date | |
| Memorandum of understanding date | 01/05/2013 |
| Date community benefit agreement completed | 01/05/2013 |
|
Link to community action plan (or similar)
|
https://www.newlucect.org/community-action-plan/ |
| Fund administrator | Developer |
| Fund administrator more details | |
| Community benefit package mechanisms | |
| Financial structure used to determine community benefits | Payment: per MW installed |
| Who makes decisions on what to fund? | Community Panel |
| Regular review of community benefits package | Yes – every 3-5 years |
| Local authorities | |
| Community councils | New Luce, Old Luce |
| Package name | Sustainable Development Fund Dumfries and Galloway |
| Fund website | https://www.sserenewables.com/communities/ |
| Planned start date | |
| Actual start date | 12/09/2013 |
| Planned end date | 10/09/2038 |
| Actual end date | |
| Memorandum of understanding date | 11/01/2021 |
| Date community benefit agreement completed | 11/01/2021 |
|
Link to community action plan (or similar)
|
|
| Fund administrator | Developer |
| Fund administrator more details | |
| Community benefit package mechanisms | |
| Financial structure used to determine community benefits | Payment: per MW installed |
| Who makes decisions on what to fund? | Stakeholder panel |
| Regular review of community benefits package | Yes – every 3-5 years |
| Local authorities | |
| Community councils | All community councils in Dumfries and Galloway |
Overview
Period start date
Report description
More details
| Period start date | 2024-04-01 |
| Period end date | 2025-03-31 |
| Funds made available this period | £30,406 |
| Additional benefits | |
| Funds spent this period | £36,232 |
| Context | Index-linked RPI |
| Further context to funds available and spent | |
| Known additional funding levered | |
| The community benefit package supports the following national outcomes | Communities, Culture, Wellbeing economy and fair work |
| Annual report link | https://www.sserenewables.com/communities/community-investment-reviews/ |
| Case study link | |
| Case study details |
| Period start date | 2024-04-01 |
| Period end date | 2025-03-31 |
| Funds made available this period | £-1 |
| Additional benefits | |
| Funds spent this period | £0 |
| Context | |
| Further context to funds available and spent | Doesnt run every year |
| Known additional funding levered | |
| The community benefit package supports the following national outcomes | |
| Annual report link | https://www.sserenewables.com/communities/community-investment-reviews/ |
| Case study link | |
| Case study details |
| Period start date | 2024-04-01 |
| Period end date | 2025-03-31 |
| Funds made available this period | £30,407 |
| Additional benefits | |
| Funds spent this period | £36,233 |
| Context | Funding rolled over to be allocated in a later funding period, Activity receiving investment was more than the funding provided in one year., Index-linked RPI |
| Further context to funds available and spent | Additional projects applied to the fund. |
| Known additional funding levered | |
| The community benefit package supports the following national outcomes | Children and Young People, Communities, Culture, Wellbeing economy and fair work, Education and learning, Health, Reduce poverty |
| Annual report link | https://www.sserenewables.com/communities/community-investment-reviews/ |
| Case study link | |
| Case study details |
| Period start date | 2024-04-01 |
| Period end date | 2025-03-31 |
| Funds made available this period | £0 |
| Additional benefits | |
| Funds spent this period | £-1 |
| Context | |
| Further context to funds available and spent | Doesnt run every year |
| Known additional funding levered | |
| The community benefit package supports the following national outcomes | |
| Annual report link | https://www.sserenewables.com/communities/community-investment-reviews/ |
| Case study link | |
| Case study details |
| Period start date | 2024-04-01 |
| Period end date | 2025-03-31 |
| Funds made available this period | £30,406 |
| Additional benefits | |
| Funds spent this period | £36,233 |
| Context | Funding rolled over to be allocated in a later funding period, Activity receiving investment was more than the funding provided in one year., Index-linked RPI |
| Further context to funds available and spent | Additional projects applied to the fund. |
| Known additional funding levered | |
| The community benefit package supports the following national outcomes | Children and Young People, Communities, Culture, Wellbeing economy and fair work, Education and learning, Health, Reduce poverty |
| Annual report link | https://www.sserenewables.com/communities/community-investment-reviews/ |
| Case study link | |
| Case study details |
| Period start date | 2024-04-01 |
| Period end date | 2025-03-31 |
| Funds made available this period | £0 |
| Additional benefits | |
| Funds spent this period | £0 |
| Context | |
| Further context to funds available and spent | Doesnt run every year |
| Known additional funding levered | |
| The community benefit package supports the following national outcomes | |
| Annual report link | https://www.sserenewables.com/communities/community-investment-reviews/ |
| Case study link | |
| Case study details |
| Period start date | 2023-04-01 |
| Period end date | 2024-03-31 |
| Funds made available this period | £29,521 |
| Additional benefits | |
| Funds spent this period | £20,226 |
| Context | Index-linked RPI |
| Further context to funds available and spent | |
| Known additional funding levered | £77,400 |
| The community benefit package supports the following national outcomes | Climate action |
| Annual report link | https://www.sserenewables.com/media/yi3bttix/2024-community-investment-review_final.pdf |
| Case study link | https://www.sserenewables.com/communities/community-investment-reviews/ |
| Case study details |
| Period start date | 2023-04-01 |
| Period end date | 2024-03-31 |
| Funds made available this period | £30,407 |
| Additional benefits | |
| Funds spent this period | £32,250 |
| Context | |
| Further context to funds available and spent | |
| Known additional funding levered | £77,400 |
| The community benefit package supports the following national outcomes | Climate action, Environment |
| Annual report link | https://www.sserenewables.com/communities/community-investment-reviews/ |
| Case study link | https://www.sserenewables.com/communities/sustainable-development-fund/ |
| Case study details |